What might indicate to a Product Owner that she needs to work more with the Scrum Team? (Choose the best answer)

What might indicate to a Product Owner that she needs to work more with the Scrum Team? (Choose the best answer)
A . The acceptance criteria do not appear to be complete.
B . People leave the Scrum Team.
C . The Increment presented at the Sprint Review does not reflect what she thought she had asked for.
D . She is not working full time with the Scrum team.

Answer: C

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments