What may be NOT decided during the INCEPTION stage of a Disciplined Agile project?

What may be NOT decided during the INCEPTION stage of a Disciplined Agile project?
A . Initial architecture
B. Deployment strategy
C. High level scope
D. Test strategy

Answer: B

Explanation:

Deployment strategy may be determined during Construction