What master data defines the quantity structure to create a standard cost estimate? There are TWO correct answers for this Question

What master data defines the quantity structure to create a standard cost estimate? There are TWO correct answers for this Question
A . Activity type
B . Routing
C . Bill of material
D . Cost center

Answer: B,C