What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?
What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?
A . Healthcare
B . Schools
C . Data centers
D . Hospitality
Answer: C
Explanation:
Data centers is the only LEED BD+C rating system that mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit. This is because data centers have unique design and operational characteristics that require a more integrative and customized approach to achieve LEED certification. The preliminary LEED meeting is intended to facilitate early goal setting, alignment, and communication among the project team members12.
Reference: LEED BD+C Reference Guide, Data Centers, page 91; LEED v4.1 BD+C: Data Centers
Latest LEED AP BD+C Dumps Valid Version with 101 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund