Data centers is the only LEED BD+C rating system that mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit. This is because data centers have unique design and operational characteristics that require a more integrative and customized approach to achieve LEED certification. The preliminary LEED meeting is intended to facilitate early goal setting, alignment, and communication among the project team members12.

Reference: LEED BD+C Reference Guide, Data Centers, page 91; LEED v4.1 BD+C: Data Centers

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments