What key elements should be included in the integration design specification when requesting approval for this Mule application?
An organization’s governance process requires project teams to get formal approval from all key stakeholders for all new Integration design specifications. An integration Mule application Is being designed that interacts with various backend systems. The Mule application will be created using Anypoint Design Center or Anypoint Studio and will then be deployed to a customer-hosted runtime.
What key elements should be included in the integration design specification when requesting approval for this Mule application?
A . SLAs and non-functional requirements to access the backend systems
B . Snapshots of the Mule application’s flows, including their error handling
C . A list of current and future consumers of the Mule application and their contact details
D . The credentials to access the backend systems and contact details for the administrator of each system
Answer: A
Explanation:
SLAs and non-functional requirements to access the backend systems. Only this option actually speaks to design parameters and reqs.
* Below two are technical implementations and not the part of design:
– Snapshots of the Mule application’s flows, including their error handling
– The credentials to access the backend systems and contact details for the administrator of each system
* List of consumers is not relevant to the design
Latest MuleSoft Integration Architect I Dumps Valid Version with 244 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund