What item(s) should the project manager develop first?
A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders. The project manager has been assigned and is now in the project planning phase
What item(s) should the project manager develop first?
A . A product backlog and identification of the features to be delivered
B . A business case and scope document
C . A communications management plan that addresses the team’s needs
D . A risk management plan to incorporate known risks
Answer: C