What is wrong with the implementation?

Refer to the exhibit.

An engineer is implementing zoning on two Cisco MDS switches. After the implementation is finished, E Ports that connect the two Cisco MDS switches becomes isolated.

What is wrong with the implementation?
A . E Ports on both MDS switches must be configured as F ports for the zoning to function.
B. Zones are local to the MDS switch and name service must be used to activate the connection between E ports.
C. Different zone set names must be configured on both MDS switches.
D. Zones must have the same name on both MDS switches for the E ports to function.

Answer: D

Explanation:

When two switches in a fabric are merged using a TE or E port, these TE and E ports may become isolated when the active zone set databases are different between the two switches or fabrics." https://www.cisco.com/c/en/us/td/docs/switches/datacenter/mds9000/sw/6_2/configuration/guides/fabric/nxos/nx_os_fabric/zone.html