What is true about Product Owner’s accountability in Nexus? Select all that apply.
A . A second Product Owner is needed
B. Scope of work increases
C. Product Owner’s accountability does not change from Scrum
D. Accountability of a product delivery shifts to Nexus Integration Team
Answer: B,C
Explanation:
The Product Owner’s accountability does not change from Scrum; the scope of the work is simply more complex. There is always one Product Owner in a Nexus and he/she is accountable for product delivery.