Exam4Training

What is true about Nexus Sprint Planning? Select two best answers.

What is true about Nexus Sprint Planning? Select two best answers.
A . Nexus Sprint Goal is crafted during Nexus Sprint Planning
B. It is better if all members of Nexus can attend to avoid communication issues
C. It is time boxed to 8 hours for a 1 month Sprint
D. Nexus Sprint Planning replaces individual teams’ Sprint Planning

Answer: A,B

Explanation:

There is no time box for Nexus Sprint Planning. It is anticipated that it’ll take longer in the initial Sprints of a product development. It is recommended for all members to attend it to avoid communication issues. Nexus Sprint Goal is also crafted during Nexus Sprint Planning.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version