What is true about Nexus Sprint Planning? Select two best answers.

What is true about Nexus Sprint Planning? Select two best answers.
A . Nexus Sprint Goal is crafted during Nexus Sprint Planning
B. It is better if all members of Nexus can attend to avoid communication issues
C. It is time boxed to 8 hours for a 1 month Sprint
D. Nexus Sprint Planning replaces individual teams’ Sprint Planning

Answer: A,B

Explanation:

There is no time box for Nexus Sprint Planning. It is anticipated that it’ll take longer in the initial Sprints of a product development. It is recommended for all members to attend it to avoid communication issues. Nexus Sprint Goal is also crafted during Nexus Sprint Planning.