What is this phenomenon called?

You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart.

What is this phenomenon called?
A . Rule of Improvement
B . Mean Improvement
C . Rule of Seven
D . Low-Riding Mean

Answer: C