What is the time-box for the Sprint Review?

What is the time-box for the Sprint Review?
A . As long as needed.
B . 2 hours for a monthly Sprint.
C . 4 hours for a monthly Sprint.
D . 4 hours and longer as needed.
E . 1 day

Answer: C

Explanation:

According to the Scrum Guide1, each event in Scrum is a formal opportunity to inspect and adapt something. These events are specifically designed to enable critical transparency and inspection.

Failure to include any of these events results in reduced transparency and is a lost opportunity to inspect and adapt. All events are time-boxed events, such that every event has a maximum duration.

Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened. The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process. The time-box for the Sprint Review is four hours for a one-month Sprint.

Reference: Scrum Guide