Exam4Training

What is the time box for Nexus Sprint Planning?

What is the time box for Nexus Sprint Planning?
A . 16 hours for one month Sprint
B. 8 hours for one month Sprint
C. 12 hours for one month Sprint
D. It is up to the Nexus Team

Answer: D

Explanation:

It is not explicitly mentioned that Nexus Sprint planning will have the same time box as the Sprint Planning. Moreover, Nexus contains multiple Scrum Teams and coordination might take longer when compared to a single Scrum Team. It is important for all the members in Nexus to agree on a ‘timebox’ but the duration is not specified in the guide. It is anticipated that it’ll take longer in the initial Sprints of the product development. It is important to have a timebox but it is up to the Nexus Team to decide the duration.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version