CORRECT TEXT
A project has an NPV of £1,200,000. The present value of material costs which are included in the NPV calculation are £8,000,000.
What is the sensitivity of the project to changes in material costs? Give your answer to the nearest whole percentage.
Answer: 15%
Latest CIMAPRA19-P03-1-ENG Dumps Valid Version with 275 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund