What is the risk with this plan?

Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time.

What is the risk with this plan?
A . The deadline is scheduled during a Salesforce release
B . The project team has decided to use the Waterfall methodology
C . The legacy system team is using an Agile methodology
D . Multiple work -streams with dependencies could impact the go-live

Answer: D