What is the risk with this plan?
Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time.
What is the risk with this plan?
A . The deadline is scheduled during a Salesforce release
B. The project team has decided to use the Waterfall methodology
C. The legacy system team is using an Agile methodology
D. Multiple work -streams with dependencies could impact the go-live
Answer: D
Latest Development Lifecycle and Deployment Architect Dumps Valid Version with 227 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments