A VxRail Test Plan has been completed
What is the protocol for recording the results’?
A . With the implementation team, complete and document each test, test date, and a screenshot of results
B . In front of a customer, complete each test and document the test date
C . With the implementation team, complete each test and document the test date
D . In front of a customer, complete and document each test, test date, and a screenshot of results
Answer: A