What is the project’s sensitivity to staff costs?
A project has a net present value of $2 million.
Total cash outflows of this project have a present value of $14 million, which includes staff costs of $10 million.
What is the project’s sensitivity to staff costs?
A . 20%
B . 63%
C . 71%
D . 14%
Answer: A
Latest CIMAPRA19-P03-1-ENG Dumps Valid Version with 275 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments