A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.
What is the project manager doing?
A . Network diagram
B. Decomposition
C. Work breakdown structure (WBS)
D. Resource leveling
Answer: B