Exam4Training

What is the project manager doing?

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?
A . Network diagram
B. Decomposition
C. Work breakdown structure (WBS)
D. Resource leveling

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version