What is the primary measurement during Inspect and Adapt?
A . Number of automated tests
B. Number of Features delivered
C. Team NPS score
D. Program predictability measure
Answer: D
Explanation:
One primary metric is the program predictability measure. Each team’s planned vs. actual business value is rolled up to create the program predictability measure
Latest SASM Dumps Valid Version with 185 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund