What is the primary measurement during Inspect and Adapt?

What is the primary measurement during Inspect and Adapt?
A . Number of automated tests
B. Number of Features delivered
C. Team NPS score
D. Program predictability measure

Answer: D

Explanation:

One primary metric is the program predictability measure. Each team’s planned vs. actual business value is rolled up to create the program predictability measure