What is the preferred time for completing racking and labeling of equipment for a new implementation?
What is the preferred time for completing racking and labeling of equipment for a new implementation?
A . After the scheduled outage has begun and initial tests have indicated success
B . Before the scheduled outage
C . At any time between the beginning of the scheduled outage and the point of no return
D . At the beginning of the scheduled outage
Answer: B
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments