What is the optimum path for success?

You organization decided to thoroughly implement the SAFe Principle "Assume variability; preserve options."

What is the optimum path for success?
A . Assume variability of scope and preserve options for the release date.
B . Preserve flexibility in system functionality and design, but have fixed Solution intent.
C . Assume variability of scope, but have fixed Solution Context.
D . Preserve flexibility in both system functionality and design.

Answer: D