What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
A . After the contract is awarded and before project close out
B . As part of the contract bid process to prevent project delays
C . Before the contract is awarded
D . At the beginning of the close out process
Answer: A