What is the name of the event where all team members determine how much of the team’s backlog they can commit to delivering during an upcoming iteration?

What is the name of the event where all team members determine how much of the team’s backlog they can commit to delivering during an upcoming iteration?
A . iteration planning
B. solution planning
C. solution demo
D. backlog refinement

Answer: A