What is the model of constraints that is used in project management called? (Select One)

What is the model of constraints that is used in project management called? (Select One)
A . Cloud Management Model
B. Resource Triangle
C. Project Model
D. Iron Triangle

Answer: D

Explanation:

The Iron Triangle (Project Triangle”), is a model of the constraints of project management: speed, cost, and quality. It contends that a project manager can trade among constraints in determining the way a project is completed. A change in one constraint necessitates changes in the others to compensate. With FinOps we would use measures such as good, fast and cheap.