What is the minimum number of freight units that are created?

You transfer two SAP ERP sales order for the same customer with the same delivery date to SAP TM Both sales order contains three items Based on customizing freight units are built automatically The freight unit building rule that is used contains the strategy "Consolidate as much as possible" No incompatibilities exist

What is the minimum number of freight units that are created?
A . 1
B . 2
C . 3
D . 6

Answer: A