Exam4Training

What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

The material cost for a project is $100,000.

What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
A . $10,000
B . $12,500
C . $22,500
D . $25,000

Answer: D

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, Option 2 of the Sourcing of Raw Materials credit requires using products that meet at least one of the responsible extraction criteria for at least 25%, by cost, of the total value of permanently installed building products in the project1. Therefore, for a project with a material cost of $100,000, the minimum material value needed to achieve this option is 25% of $100,000, which is $25,000.

Exit mobile version