What is the key concern when multiple Development Teams are working from the same Product Backlog?

What is the key concern when multiple Development Teams are working from the same Product Backlog?
A . Minimizing dependencies between teams.
B . Clear definition of requirements.
C . Meeting original scope projections.
D . Making sure there’s enough work for everyone on every team.
E . Maximizing velocity.

Answer: B

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
7 Comments
Inline Feedbacks
View all comments
LouisCyphre
LouisCyphre
4 years ago

It is A. Source: Nexus Open Assesment

E
E
5 years ago

It is A. PB items cannot be possibly clear in an agile framework as Scrum

Erik
Erik
5 years ago

My initial answer is also be A

With good descriptions you will not solve the dependency problems.

Daniel
Daniel
5 years ago

I would also say the correct one is A

Przemyslaw
Przemyslaw
5 years ago

It should be answer A.
The dependencies between teams cause that the single team is not able to deliver the working Increment. Besides in Scrum you work with PBIs, not with requirements.

younessben
younessben
5 years ago
Reply to  Przemyslaw

I was looking if anyone left a comment about it , indeed it should me A

Lawrence
Lawrence
4 years ago
Reply to  younessben

It is not A because there must be no dependencies between the Product Backlog Items. Minimizing dependencies is something that should be done since the start, and the fact there are several Development teams has nothing to do with it.