What is the ideal approach for an Agile project manager to take when considering fractional assignments?

What is the ideal approach for an Agile project manager to take when considering fractional assignments?
A . Do nothing, as fractional assignments will not impact project performance.
B . Allow resources to be assigned to no more than two projects at a time.
C . Only allow nonessential resources to be fractionally assigned.
D . Avoid them and have resources assigned to only one project at a time.

Answer: D