A company has a requirement to report on actual labor hours, materials, services and tools used as work progresses on a work order.
What is the earliest point in the basic life cycle a user can start reporting?
A . APPR
B . COMP
C . WMATL
D . WAPPR
Answer: A
Explanation:
Reference: http://www-01.ibm.com/support/docview.wss?uid=swg21683844