What is the document that defines the activities, deliverables and timelines a supplier must carry out during contract performance?

What is the document that defines the activities, deliverables and timelines a supplier must carry out during contract performance?
A . Statement of work
B . Project initial document
C . Framework agreement
D . Work instruction

Answer: A

Explanation:

Statement of Work (SoW) is the document that captures and defines all aspects of your project. You’ll note the activities, deliverables and the timetable for the project. It’s an extremely detailed document as it will lay the groundwork for the project plan.

Project Initial Document is an important document and should precede any specification writing project. It sets out the scope of the project and it is the team’s mandate from senior management Work instructions are also called work guides, Standard Operating Procedures (SOPs), job aids or user manuals, depending on the situation. In any case, the purpose of work instructions is to clearly explain how a particular work task is performed.

Framework agreements are arrangements between one or more buyers and one or more suppliers that provide the terms governing contracts to be established for a certain period of time, in particular with regard to price and, where necessary, the quantity envisaged.

Reference: CIPS study guide page 124

LO 3, AC 3.1

Latest L4M2 Dumps Valid Version with 144 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments