Site icon Exam4Training

What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question.

What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question.

A. Custom code is adjusted in System Conversion and developed in New Implementation of SAP V U S/4HANA in the Realize phase.

B. Data is migrated in System Conversion and converted in New Implementation of SAP □ S/4HANA in the Realize phase.

C. Custom code is developed in System Conversion and adjusted in New Implementation of SAP u

S/4HANA in the Realize phase. 4

D. Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase.

Answer: A, D

Explanation:

A is correct because custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing custom code needs to be adapted to run on SAP S/4HANA. In New Implementation, new custom code needs to be developed to meet the customer’s specific requirements.

D is correct because data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing data needs to be converted to the new data structures and formats of SAP S/4HANA. In New Implementation, new data needs to be migrated from the legacy system or other sources to SAP S/4HANA.

Verified Reference: SAP Activate Project Management Certification Guide, page 127