A company wants to deploy VxRail on V Series nodes as a proof-of-concept (POC). Only one Top of Rack (ToR) switch has been provided for the POC.
What is the Dell EMC best practice recommendation in this situation?
A . Connect the first host NIC to the ToR switch. Leave the second host NIC un-cabled.
B . Connect each host NIC to a port on a different switch packet buffer bank on the ToRswitch. Balance the ports across two packet buffer banks.
C . Inform the company that the POC cannot proceed without a second ToR switch.
D . Connect the first host NIC to the TOR switch. Daisy chain the second NIC between hosts.
Answer: B