What is the correct sequence of activities that takes place during the Maven build and deployment?

A company has been using CI/CD. Its developers use Maven to handle build and deployment activities.

What is the correct sequence of activities that takes place during the Maven build and deployment?
A . Initialize, validate, compute, test, package, verify, install, deploy
B . Validate, initialize, compile, package, test, install, verify, verify, deploy
C . Validate, initialize, compile, test package, verify, install, deploy
D . Validation, initialize, compile, test, package, install verify, deploy

Answer: C

Explanation:

The correct sequence of activities that takes place during the Maven build and deployment is validate, initialize, compile, test package, verify, install, deploy. These are Maven lifecycle phases that define a sequence of goals to execute during a build process. Each phase represents a stage in the build lifecycle and can have zero or more goals bound to it.

References: https://maven.apache.org/guides/introduction/introduction-to-the-lifecycle.html