What is the core benefit of the Principle #4 C Build incrementally with fast, integrated learning cycles?
A . It enables the shortest sustainable lead time, by eliminating impediments to the flow of work
B. It enables risk to be evaluated early, through early validation and feedback.
C. It ensures the right work gets done, and the wrong work doesn’t; by informing and driving decisions at all levels to best identify the value of work being done
D. It gives a better picture of actual progress, by being focused on building the system in increments, with evidence at each increment point of objective and data based measurement towards achieving the outcome
E. It provides better focus for multiple solutions and allows teams to concentrate and focus on the variable elements of work
F. It improves solution development by enhancing the understanding of the system and the environment and applying that understanding to design, develpment, deployment, and maintenance of the system itself
Answer: B
Explanation:
The core benefit of principal # 2 is "It enables risk to be evaluated early, through early validation and feedback".
For more details: https://www.scaledagileframework.com/safe-lean-agile-principles/#:~:text=%234%20%E2%80%93%20Build%20incrementally%20with%20fast,build%20on%20the%20previous%20ones.