What is the consequence for the corresponding shop order in the shop floor system?

You apply the Integration of Manufacturing Execution System to Production Operation (1Y5) scope item and the production supervisor changes the quantity of a released production order in SAP S/4 HANA Cloud.

What is the consequence for the corresponding shop order in the shop floor system?
A . The shop order is deleted and a new shop order with the new quantity is created
B . The shop order is flagged for manual change in the shop floor system
C . The shop order is updated asynchronously by a daily background job
D . The shop order is changed automatically in the shop floor system

Answer: D