What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
A . Steering committee meeting decision
B . Definition of Done for User Story
C . Agreed and met Acceptance Criteria within quality gate
D . Definition of Done for Sprint
Answer: C