What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?

What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
A . Steering committee meeting decision
B . Definition of Done for User Story
C . Agreed and met Acceptance Criteria within quality gate
D . Definition of Done for Sprint

Answer: C