What is required in inspection planning to transfer a characteristic value from results recording of inspection lot processing………

What is required in inspection planning to transfer a characteristic value from results recording of inspection lot processing………
A . Configuration settings
B. Settings for the inspection type activated in the material level
C. Master inspection characteristic linked to class characteristics
D. Usage of the class characteristics in the task list

Answer: C

Explanation:

In SAP Quality Management, to transfer a characteristic value from results recording during inspection lot processing, it is essential to have:

Option C. Master inspection characteristic linked to class characteristics.

This linkage ensures that the values recorded for the master inspection characteristic can be mapped and transferred to the corresponding class characteristics.