What is one requirement to combine Aruba 5400R zl2 Series switches in a Virtual Switching Framework (VSF) fabric?
What is one requirement to combine Aruba 5400R zl2 Series switches in a Virtual Switching Framework (VSF) fabric?
A . Both of the members must have two management modules.
B . The switches must operate in v3-module only mode; any modules of an earlier version are automatically disabled.
C . The interfaces assigned to the VSF link must be pre-configured as part of a link aggregation.
D . One of the switches must be an Aruba 5412R switch, while the other member can be any switch in the 5400R series.
Answer: D
Answer is wrong. Correct option is B
VSF fabric must contain 2 Aruba 5406R or 2 Aruba 5412R switches, not one Aruba 5406R and one Aruba 5412R combined. So option D is out.
The physical interfaces associated with the VSF link cannot be members of link aggregations (trunks), meshes, distributed trunks, or in an inter switch connect (ISC) associated with distributed trunking (DT). So option C is out.
When part of a VSF fabric, a 5400R switch can only use one management module, and enabling VSF de-activates a second management module. It is recommended, though, that you install only one management module in the switch. So option A is out
The switches must operate in v3-module only mode; any modules of an earlier version are automatically disabled. Is the correct answer