What is one anti-pattern of the Inspect and Adapt?
A . No actionable improvement Features are created
B . Not enough team members attend the PI System demo
C . Too many ideas enter the problem-solving workshop
D . Only one problem is identified by each team in the retrospective
Answer: A
Explanation:
One anti-pattern of the Inspect and Adapt (I&A) is to have no actionable improvement Features created as a result of the problem-solving workshop. This is considered an anti-pattern because the main goal of the I&A workshop is to identify and address the systemic issues that are limiting the effectiveness of the Agile Release Train (ART). The workshop should produce one or more improvement Features that are added to the ART backlog and prioritized for the next PI Planning event. These Features should be SMART (Specific, Measurable, Achievable, Relevant, and Time-bound) and aligned with the ART vision and goals. Without actionable improvement Features, the ART will miss the opportunity to learn and improve from the feedback and data collected during the PI.
Reference: Inspect and Adapt – Scaled Agile Framework
Exam Study Guide: SSM (6.0) – SAFe® Scrum Master
based on SAFe 60 methodology What is one antipattern of the
Latest SSM Dumps Valid Version with 204 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund