What is an off-specification?
What is an off-specification?
A . A new requirement
B . A quality tolerance
C . A type of issue
D . A major risk
Answer: C
Explanation:
An off-specification in PRINCE2 is considered a type of issue that arises when a project deliverable is forecasted to deviate from its agreed-upon specifications or requirements. It is an important part of the issue and change control procedure in PRINCE2, where it’s recognized and managed to ensure the project stays aligned with its objectives.
Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website