What is an input to the Program Increment Planning process that highlights how Product Management plans to accomplish the Vision?
A . Top ten Features
B. Program board
C. Business context
Answer: A
Explanation:
Inputs to PI planning include: Business context (see ‘content readiness’ below) Roadmap and vision Top 10 Features of the Program Backlog A successful PI planning event delivers two primary outputs: Committed PI objectives C A set of SMART objectives that are created by each team with the business value assigned by the Business Owners. Program board C Highlighting the new feature delivery dates, feature dependencies among teams and relevant Milestones.