What is a strategy a Product Owner can use during Program Increment Planning to minimize dependencies?

What is a strategy a Product Owner can use during Program Increment Planning to minimize dependencies?
A . Change the definition of done
B. Move Stories on their team’s backlog to another team
C. Reprioritize Epics

Answer: B

Explanation:

Dependecy can be addressed through ROAMing activity, if story is depending on other team, then PO can move story on another teams backlog.