What is a Development Team responsible for? (Choose two.)
A . Resolving internal team conflicts.
B . Reporting productivity.
C . Selecting the Product Owner.
D . Organizing the work required to meet the Sprint Goal.
Answer: A,D
Explanation:
The correct answers are A and D, because a Development Team is responsible for resolving internal team conflicts and organizing the work required to meet the Sprint Goal. The Scrum Guide states that “development Teams are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality.” Therefore, a Development Team should manage its own work and resolve its own issues.