What information should the project manager use as an indicator that the project is actually delivering value?
During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status.
What information should the project manager use as an indicator that the project is actually delivering value?
A . Stakeholders are satisfied with the current status.
B . The project is under budget and on schedule
C . The project is aligned with the project charter
D . The protect is aligned with the benefits management plan
Answer: D