What impact does this have on the project progress status?
A team member has five days to complete a critical path task, and the task requires only one hour.
Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
A . The next team member cannot start his task.
B . No impact as the task is not overdue.
C . The project shows an At Risk automatic condition.
Answer: C
Explanation:
In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront’s automated system flags the project as "At Risk" if there is a delay in progress that could impact the project’s timeline. This "At Risk" condition acts as a warning to project managers and stakeholders that immediate attention is needed.