What immediate action should the project manager take to improve the situation?

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?
A . Communicate this issue to the human resources department.
B . Provide additional training to the new hire.
C . Increase team cohesiveness by sharing information and experiences openly.
D . Update the issue log and define the mitigation strategy.

Answer: D