What has happened in this situation?

A project manager for a maintenance project has a contract that is renewed annually. The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?
A . The contract has not been appropriately reviewed by the project team
B . The stakeholder engagement plan has not been correctly implemented
C . The legal department has not disseminated the law correctly to all staff.
D . The project manager does not have enough knowledge on this legal matter

Answer: C