What happens to the next planned date if you set the shift factor for early completion to 100%?

The technical completion of the current maintenance order was posted with a delay of 5 days.

What happens to the next planned date if you set the shift factor for early completion to 100%?
A . It is not shifted.
B. It is postponed by 5 days.
C. It is postponed by a full cycle(100%).
D. It will be 5 days earlier.

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments