What happens to improvement items identified during the Iteration Retrospective?

What happens to improvement items identified during the Iteration Retrospective?
A . They are ROAMed with the rest of the risks
B. They are given to the Scrum Master who resolves them
C. They are entered as Stories in the Team Backlog

Answer: C

Explanation:

When issues have been identified, root cause analysis is performed, potential corrective actions are discussed, and improvement Stories are entered into the Team Backlog.